Arizona Department of Transportation SR 179 Improvement Project
(800) 529-2876 www.scenic179.com pr@scenic179.com
Welcome to the State Route (SR) 179 Project Weekly Construction Update - your electronic connection to the SR 179 Project with the most current information on construction plans and activities.
Please note: Changes to construction plans can happen frequently due to weather, equipment availability and personnel issues. We try to anticipate construction activities a week in advance but changes may occur. Intermittent lane closures, with short delays, may not always be known in advance.
For a complete listing of freeway and highway restrictions across Arizona visit ADOT's Travel Information Site at www.az511.com or call 5-1-1.
What to Watch for Week of October 15
ADOT is committed to continuing work with the community throughout this roadway improvement project. Please remember that two-way traffic is continuing to flow, and business access is clearly marked.
Work South of the Village of Oak Creek
The pedestrian path that will connect the new Forest Ranger Station with the Village of Oak Creek is taking shape along the east side of SR 179. A wireline is installed to prepare for the curb and gutter work. Utility companies also are working on the east side of the road to bring services to the new Ranger Station.
Work in the Village of Oak Creek
Traffic has been switched onto new pavement on the east side of SR 179 through most of the Village of Oak Creek. Crews will be working from south to north to install the new driveways along the route. Representatives of the team are working with each business along the way to coordinate the driveway work. Watch for blue business access signs to guide you to businesses.
The first modern roundabout intersection to be completed in the Village of Oak Creek will be at Ridge Trail, followed by Bell Rock Boulevard. The Jacks Canyon and Cortez intersections also will function using modern roundabouts.
Work in the Forest
The two new bridges are nearly complete, and cleanup work is underway. The entire new alignment is graded and being prepared for pavement. All work is being closely coordinated with the US Forest Service.
Work in Sedona
The first roundabout to be completed on the entire project will be at Back O Beyond Road. Final preparations are underway to complete this roundabout, and traffic is moving through the intersection. Please be attentive to the instructions of flaggers.
Utility companies also are working in the city limits to move their lines, pipes, and cables out of the way of the upcoming road improvements.
If you have information for the Scenic 179 construction updates, please send it to pr@scenic179.com or fax to 928-204-9835. To change your e-mail address, add someone new, or request a text version of this update, please e-mail pr@scenic179.com. |