SR179 Construction Update

Arizona Department of Transportation SR 179 Improvement Project
(800) 529-2876 www.scenic179.com pr@scenic179.com

Welcome to the State Route (SR) 179 Project Weekly Construction Update - your electronic connection to the SR 179 Project with the most current information on construction plans and activities.

Please note: Changes to construction plans can happen frequently due to weather, equipment availability and personnel issues. We try to anticipate construction activities a week in advance but changes may occur. Intermittent lane closures, with short delays, may not always be known in advance.

What to watch for the week of January 15:

SR179 Construction

One lane of traffic continues to flow in each direction throughout the construction areas. Intermittent driveway closures will be necessary for the installation of drainage pipe, construction of curb, gutter, sidewalk and driveways. These closures will be minimized to the fullest extent possible. Individual businesses will be given advance notice of these closures. As always, business access will be maintained. Watch for blue “business access” signs to guide you, and please drive with care through the area.

Construction of a retaining wall is ongoing south of the Village of Oak Creek where traffic has been shifted westward onto temporary pavement. There may be minor traffic impacts such as shoulder closures or construction vehicles needing access to the road, or lane closures of short durations with flaggers/DPS present.

Drainage work between the new Ranger Station and Ridge Trail Drive is ongoing. There may be minor traffic impacts such as shoulder closures or construction vehicles needing access to the road, or lane closures with flaggers/DPS present.

Jacks Canyon Drainage WorkJacks Canyon Road currently is projected to be reopened by the end of January.

Work for new bridge construction in the forest segment is ongoing near milepost 309.5. There may be some flag people providing traffic control in this area to allow trucks in and out. The HT Trail will be closed until Spring 2007 for bridge construction.

Traffic at Back O Beyond will be shifted to the east side of the road on January 16, so storm drain work can begin on the west side. Temporary concrete barrier will be installed to help traffic flow. There may be intermittent lane closures with flaggers/DPS present.

Communications

Construction Chat will be held monthly on the first Thursday of each month. The next scheduled Construction Chat is February 1, from 7 to 9 a.m., at the SR 179 Project Office.



If you have information for the Scenic 179 construction updates, please send it to pr@scenic179.com or fax to 928-204-9835. To change your e-mail address, add someone new, or request a text version of this update, please e-mail pr@scenic179.com.